Srinagar, Jul 12: The long-awaited dream of traveling to Kashmir by train is closer to reality as significant progress has been made on the Udhampur-Srinagar-Baramulla Rail Link (USBRL) project. Tunnel T-15 and part of Tunnel T-14 has been completed, marking substantial milestones in this ambitious infrastructure endeavor.
The completion of these tunnels is seen as a pivotal step in enhancing all-weather connectivity between the Kashmir Valley and the rest of India. As per the officials associated with the project, the USBRL project, set in the challenging Himalayan terrain, required advanced tunneling techniques including heading, benching, invert excavation, kerb concreting, and the installation of Geo-textile, Geo-membrane, reinforcement, and concrete lining.
To address geological challenges such as loose rocks during tunnel blasting, an umbrella-type pipe roofing system was implemented. The New Austrian Tunneling Method (NATM) technology was employed, involving approximately 1,600 skilled and semi-skilled workers during the peak construction phase.
Spanning 272 kilometers, the USBRL project is of national importance and promises to transform transportation in the region. The Indian Railways conducted a successful trial run from Sangaldan to Reasi at a speed of 110 km/hr, navigating through Tunnel T-15 and part of Tunnel T-14. (KNO)
Take Red Cross services closer to people: Lt Governor
Srinagar, Aug 31: Emphasising the need to take Red Cross services closer to the people, Lieutenant Governor Manoj Sinha on...






